Draw the task relationships diagram, and identify earliest start/finish times, as well as latest start/finish times, slack, and critical path.

ASSIGNMENT A project is broken down into 8 tasks–A to H–with given duration times and predecessors. Task Duration Predecessor A 3 B 4 C 4 A, B D 5 A E 2 A, B F 8 C, D G 4 D, E H 3 F, G Draw the task relationships diagram, and identify earliest start/finish […]