PERT network Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES (days) to tml tp te A — 6 6 6 B A 4 5 6 C A 2 4 6 D B 4 6 8 E C 2 4 6 F D 1 5 3 1) Construct a PERT network. [NOTE: This is the […]
PERT network Consider the following table: ACTIVITY PREC. ACT. TIME ESTIMATES (days) to tml tp te A — 6 6 6 B A 4 5 6 C A 2 4 6 D B 4 6 8 E C 2 4 6 F D 1 5 3 1) Construct a PERT network. [NOTE: This is the […]