linear schedule

Using a minimum float guideline of 1 day, develop a linear schedule for this project. What is the project duration if no activities are to be interrupted?

Construction A project consists of replacing the track on an existing railroad line, involving 3,000 feet of track. The old track can be removed at a rate of 70 feet per hour. The old rail- road ties can be removed at a rate of 200 feet (measured along the track) per hour. The new ties […]