Crash time

Draw a network diagram and establish the Critical Path. Calculate the normal cost to complete the project given that the fixed cost amounts to $150 per day.

Network Analysis QUESTION 3 Munyash construction has tabled the following activities to be rolled out for the up-coming project in Midlands. Activity Preceding Activity Normal time in days Crash time in days Normal costs S Crash costs $ A-B 5 3 650 850 A-C – 6 3 750 1 050 A-E – 8 7 950 […]

Scroll to top