MS Project Assignment
You are on an implementation team which has received a task order to install an MS 2019 Server.
Your MS Project Assignment File MUST be named (-5 points if you get this wrong):
IT 343 MS Project Assignment – <<First Name>> <<Last Name>>.mpp
Where <<First Name>> <<Last Name>> is YOUR first name and last name (not mine)
The design team has forwarded the following top level WBS to you:
WBS Major Task Names (also called a work package)
Plan for Project Server 2019 deployment
Prepare for deployment
Install SharePoint Server 2019
Install and configure Project Server 2019
Create the Project Web App site
Your assignment is to create a MS Project plan with the following qualities:
The first line in your Gantt Chart must be your Name and MS Project Assignment
Use the above-supplied WBS as a top-level summary task structure
A minimum of two second level tasks for each summary task
A minimum of 25 work packages for the overall project
Assign 6-9 resources (at least 4 employees and 2 Hardware/Software resources) with appropriate hourly rates for assignment to work packages
Ensure there is no resource over allocation
Ensure the work packages have proper durations and predecessors
Configure the project to last a MINIMUM OF 4 months and a MAXIMUM 6 months (or between 90 and 130 days).
Ensure there is cost data in the Gantt Chart. Your total cost must be between $50,000 and $75,000
Ensure there are Milestones for each major task level (reference the list of WBS Major Task Names above (i.e., Plan for Project Server 2019 deployment, Prepare for deployment, etc