ASSIGNMENT
A project is broken down into 8 tasks–A to H–with given duration times and predecessors.
Task Duration Predecessor
A 3
B 4
C 4 A, B
D 5 A
E 2 A, B
F 8 C, D
G 4 D, E
H 3 F, G
Draw the task relationships diagram, and identify earliest start/finish times, as well as latest start/finish times, slack, and critical path. (60 points)
Draw the Gantt chart and identify the critical path and slacks with different colors. (40 points)
Draw the task relationships diagram, and identify earliest start/finish times, as well as latest start/finish times, slack, and critical path.