Assignment
Imagine that you are a project manager for a construction company. You must create a WBS for the Site Preparation phase of this project. Here is a list of tasks.
Task | Title | Predecessors | Duration |
A | Contract Approval | — | 5 |
B | Site Survey | A | 5 |
C | Permit Application | A | 4 |
D | Grading | B,C | 5 |
E | Sewer Lines | B | 7 |
F | Base Paving | D | 3 |
G | City Approval | C,F | 6 |
H | Final Paving | E,G | 8 |
Create a WBS for the Site Preparation phase of this project.