What duration should be used in your schedule if you want to ensure 95% confidence that the activity’s duration will not be exceeded?

Scheduling and Planning

Question 1 (10 points). Historic records show that the mean duration of an activity is expected to be 8 days with a standard deviation of 2.4 days.
a) What duration should be used in your schedule if you want to ensure 95% confidence that the activity’s duration will not be exceeded?

b) What it the probability that the duration will actually exceed 10 days?

Question 2 (10 points). Based on the network below, what are the probabilities (in percentages) of completing the project within the following durations:
a) 55 days?

b) 60 days?

c) 65 days?

B-
14/20/40
D
17/25/55
F-
8/12/20
C
10/15/20
E –
10/14/20
G-
25/30/50
START
Activity
TO / TM / TP

Question 3 (10 points). Based on the network below, what are the probabilities (in percentages) of completing the Critical Path within:
a) 24 days

b) 32 days

START Activity

B-
2, 4, 6
D-
5, 6, 7
H
1, 1, 1
C
2, 3, 10
E
2, 2, 8
G
1, 2, 3 FINISH
FINISH

J
2, 5, 8
F
6, 7, 8
I-
5, 8, 17
K
1, 2, 9
L-
1, 3, 11
TO, TM, TP

What duration should be used in your schedule if you want to ensure 95% confidence that the activity’s duration will not be exceeded?