Produce a sketch of the vertical section along the line of levelling survey and explain the process/procedures you have taken to accurately carry out the levelling survey.

Faculty of Computing and Engineering Sciences

Project Brief:

Part 1: Vertical control

 As part of the pre-design information required for the re-development of the K- block within the University of South Wales’s Treforest campus, some surveying activities are needed to be implemented around the development site. The survey activities involve a closed levelling survey, where reduced levels are required for various observation/stake points as indicated below and shown in Appendix 1.

Point A – Top of drain cover 1 Point B – Top of RC wall Point C – Top of drain cover 2 Point D – Top of pavement Point E – Top of bottom stairs Point F – Top of drain cover 3 Point G – Top of drain cover 4 Point H – Top of corner kerb Point I – Top of drain cover 5

The reduced level for the Temporary benchmark (TBM)  was identified as 69.650m.

Using the rise and fall method sheet in Appendix 2, conduct a levelling survey of the identified observation/stake points around the development site (Refer to practical survey Risk Assessment in Appendix 4).

Record the data obtained from the various line of sights (intermediate sights and fore sights) in your booking

Evaluate the Reduced Levels (RL) on the booking sheet and carry out the mathematical

Verify the accuracy of the levelling survey and comment

Produce a sketch of the vertical section along the line of levelling survey and explain the process/procedures you have taken to accurately carry out the levelling survey (Note: the sketch should not be hand-drawn but produced with applications such as CAD, Excel ).

Part 2: Horizontal control

Using a Total station, the horizontal angular measurement of some identified target points are required to be taken from specific station positions within the K-block site (Refer to practical survey Risk Assessment in Appendix 4).

a)    Record the horizontal circle readings for the target points in the booking sheet shown in Appendix 3.

b)    Determine the mean horizontal circle readings for the identified target points from your allocated instrument position.

c)    Evaluate the mean horizontal angles for the target points.

d)    Describe with annotated sketches the process you obtained the horizontal angular measurements on-site using a Total Station from your allocated instrument position.

 Proposed K-Block

Observation or stake points

Appendix 2: Levelling survey booking sheet

  Survey of   Instrument  
Surveyor   Datum used  
Date  

 

Backsight

BS [m]

Intermediate

IS [m]

Foresight

FS [m]

Rise Fall Reduced Level

RL [m]

Distance

[m]

Remarks
1.572         69.650   TBM
  1.505   0.067   69.717   A
  0.917   0.588   70.305   B
1.494   1.473   0.556 69.749   C
  1.277   0.217   69.866   D
  1.520     0.243 69.723   E
1.639   1.855   0.355 69.388   F
  1.542   0.097   69.485   G
1.561   1.592   0.050 69.435   H
  1.430   0.131   69.566   I
    1.341 0.089   69.655   TBM
               
Maths check              
∑=6.266   ∑=6.261 ∑=1.189 ∑=1.184 Last RL – First RL    
∑BS – ∑FS = ∑Rise – ∑Fall =0.005 =0.005   Maths check =OK
              Allowable misclosure check
              ±5√n = 10.000mm = 0.01m

 

Appendix 3: Angular measurement booking sheet

Station position

Target point

Horizontal circle                   Mean Horizontal Circle Face right      Face left                                          Readings

Mean Horizontal              Remarks Angles

A                00,07’,44”              180,07’,40”                  86,34’,58”                          86,35’,02”

B                86,42’,42”             266,42’,46”                   86,35’,06”

B                00,33’,42”             180,33’,57”                   51,41’,29”                          51,40’42”

C                52,15’,08”             232,14’,09”                   51,40’,12”

…………

C                00,23’,44”             180,18’,16”                   18,28’,40”                          18,28’39”

D                18,52’,24”             198,52’,38”                   18,28’,39”

D                00,18’,17”             180,18’,16”                   45,25’,23”                           45,25’,23”

E                45,43’,40”              225,43’,42”                   45,25’,26”

 

Produce a sketch of the vertical section along the line of levelling survey and explain the process/procedures you have taken to accurately carry out the levelling survey.
Scroll to top